New construction vs. replacement

New construction means the window goes in while the wall is still open — full framing access, and the unit is held by a fin (Nail-Fin on Stick Framed, or a Florida Flange / leg on Block Framed). Replacement (retrofit) drops a new frame into the existing opening of a finished house, so you favor finless block frames, flush fins, or a Florida Flange / Replacement unit. This single choice swings labor more than anything else: roughly 10 min/LF for stick-framed new work versus about 40 min/LF on a remodel. Block Framed adds its own load on top — wood bucking, block sealer, and concrete (Tapcon) anchors.

Pros

  • New construction is faster per foot (~10 min/LF) and lets the fin lap into the weather barrier for a cleaner water seal.
  • Replacement avoids tearing into finished walls — less patching of stucco, drywall, and trim for the homeowner.
  • Florida Flange / Replacement and finless block frames are built to slip into an existing opening, so the visible footprint stays small.

Watch-outs

  • Replacement runs ~40 min/LF — about 4x the labor of new stick work — because of surface protection, fitting, and sealing back to finished walls.
  • New construction only works while the wall is open, so it's not an option on a finished house.
  • Block Framed (either path) adds wood bucking, block sealer, and concrete anchors — more material, more time, and Tapcon drilling into masonry.